Nigeria’s fragile electricity system suffered another setback on Monday as the national power grid collapsed, leading to widespread outages across several parts of the country.
Checks showed that electricity supply dropped drastically following the system disturbance, with total load on the grid falling to about 50 megawatts as of 3:12pm on December 29, 2025.
Load allocation data from electricity distribution companies indicated that Ibadan Electricity Distribution Company received 30MW, while Abuja DisCo got 20MW. All other distribution companies — Benin, Eko, Enugu, Ikeja, Jos, Kaduna, Kano, Port Harcourt and Yola — recorded zero megawatts at the time.
Confirming the development, the Abuja Electricity Distribution Company said a system disturbance occurred on the national grid at about 2:02pm, causing power outage across its franchise areas.
“We wish to inform you that a system disturbance occurred on the national grid at 14:02pm today, causing power outage across our franchise areas,” the company said in a post on X, adding that it was working with relevant stakeholders to restore supply once the grid is stabilised.
Other distribution companies also confirmed the collapse of the grid, which resulted in nationwide disruption of electricity supply.

However, the Eko Electricity Distribution Company later announced that the national grid had been restored and that power supply was gradually returning to its network.
“The national grid has been restored and restoration of power supply to our feeders is progressing gradually,” Eko DisCo said.
As at press time, the Transmission Company of Nigeria had yet to issue an official statement on the latest grid collapse.
The latest incident adds to a growing list of grid collapses recorded in 2025, raising renewed concerns over the stability and resilience of Nigeria’s power infrastructure, despite repeated assurances by the Federal Government.
In August, the Federal Government disclosed plans to secure a $238 million loan from the Japan International Cooperation Agency to expand and strengthen the national electricity grid.
The loan, according to the government, followed the approval of ₦19 billion by the Federal Executive Council as counterpart funding to unlock the JICA facility.
The funds are expected to be deployed for the expansion of the national grid, including the construction of 102.95 kilometres of new 330kV double-circuit lines, 104.59 kilometres of new 132kV double-circuit lines, four 330/132/33kV substations, two 132/33kV substations, and extensions of existing 330kV and 132kV line bays.