The Federal Government has commissioned upgraded transmission substations at Ijora and Apapa Road in Lagos, adding a combined 208 megawatts of bulk transmission capacity to the national grid.

The projects, inaugurated by the Minister of Power, Joseph Tegbe, are expected to boost electricity supply to major industrial, commercial and residential areas across Lagos.

At the Ijora 132/33kV transmission substation, two new 100MVA transformers have raised the installed capacity from 90MVA to 230MVA, providing an additional 112MW of bulk transmission capacity.

The upgrade is expected to improve power supply to Ijora, Costain, Oyingbo, Customs and adjoining communities within the franchise area of the Eko Electricity Distribution Company.

At the Apapa Road transmission substation, two new 60MVA transformers and modern Gas Insulated Switchgear were installed and energised, increasing the facility’s capacity from 60MVA to 180MVA and adding another 96MW to the transmission network.

The Apapa project is considered particularly important because the area hosts major ports, maritime businesses, logistics companies, warehouses and manufacturing industries. The additional capacity is expected to increase the bulk electricity available to EKEDC for distribution to Apapa Causeway, Ijora, Amukoko, Ajegunle, Apapa Wharf, Tin Can Island and surrounding communities.

Speaking at the commissioning, Tegbe said the projects were part of the Federal Government’s efforts to tackle structural challenges in the nation’s electricity sector.

He said expanding transmission capacity was essential to ensuring that electricity generated was effectively delivered to areas where demand was highest.

According to him, rapid population growth, industrial expansion and increased commercial activities had put considerable pressure on existing power infrastructure, resulting in suppressed load and constrained electricity supply.

Tegbe said reliable electricity remained central to Nigeria’s economic transformation, adding that the administration’s ambition of building a $1tn economy could not be achieved without adequate and dependable power supply.

The Managing Director and Chief Executive Officer of the Transmission Company of Nigeria, Sule Ahmed Abdulaziz, described the projects as a significant investment in strengthening the country’s transmission network. He said the Apapa project was supported by the Japan International Cooperation Agency, while the Ijora intervention received support from the World Bank in partnership with TCN.

Abdulaziz called for similar interventions to rehabilitate and upgrade other critical sections of the national transmission network. He said continued investment in the network was necessary to ensure that improvements in power generation translated into better supply for homes and businesses.

The Federal Government said the additional 208MW would improve grid stability and strengthen electricity supply to some of Lagos’ most important commercial and industrial corridors, with the projects expected to support businesses and communities that depend heavily on reliable power.